Where your home is right now

Here is exactly where your home is. We update this as each stage completes, so you always know what is happening and what comes next.

Overall progress
50%
4 of 8 stages complete
Current stage
Lock-up
Reached 10 June 2026
Settlement
102 days
Estimated 26 September 2026

47 Yeovil Road build timeline

  1. Building consent

    Complete

    Consent granted by Auckland Council.

    Completed12 September 2025
  2. Site works & foundation

    Complete

    Earthworks complete, foundation poured and cured.

    Completed20 November 2025
  3. Framing

    Complete

    Timber framing up, pre-line inspection passed.

    Completed18 February 2026
  4. Roof & cladding

    Complete

    Roof on, cladding and joinery installed, weathertight.

    Completed30 April 2026
  5. Lock-up

    In progress

    Your home is now at lock-up. Interior fit-out begins.

    Completed10 June 2026

    This is where your home is right now. We update this stage as soon as the next inspection is signed off.

  6. Interior fit-out

    Linings, kitchen, bathrooms, flooring and finishes.

    Estimated25 July 2026
  7. Practical completion & CCC

    Final inspections and Code Compliance Certificate.

    Estimated10 September 2026
  8. Settlement & handover

    Keys to your new home.

    Estimated26 September 2026

Dates marked “Estimated” are our best forecast and can shift with weather, inspections and supply. We will always update this page and let you know if anything changes.